Travel Information

Short Term

6/11/21 to 6/18/21
LANE CLOSURE: US 183 southbound right frontage lane from US 290 to Manor Springdale Rd.
Lane Closure | Retaining Wall Construction

Lane Closure
Friday (6/11) 9 a.m. to 3 p.m., Monday-Friday (6/14-6/18) 9 a.m. to 3 p.m., US 183 southbound right frontage lane will be closed from US 290 to Manor Springdale Rd.

Retaining Wall Construction

6/14/21 to 6/18/21
LANE CLOSURE: US 183 southbound left frontage lane Montopolis to Patton Ave.
Lane Closure | Guardrail Work

Lane Closure
Monday-Friday (6/14-6/18) 9 a.m. to 3 p.m., US 183 southbound left frontage lane will be closed from Montopolis to Patton Ave.

Guardrail Work

6/14/21 to 6/17/21
LANE CLOSURE: US 183 northbound right mainlane will be closed Smith Rd. to Hudson St.
Lane Closure | Retaining Wall Construction

Lane Closure
Monday-Thursday (6/14-6/17) 9 a.m. to 3 p.m., US 183 northbound right mainlane will be closed from Smith Rd. to Hudson St.

Retaining Wall Construction

6/14/21 to 6/17/21
LANE CLOSURE: Westbound SH 71 left mainlane Old Bastrop Hwy to E. Riverside Dr.
Lane Closure | Utility Work

Lane Closure
Monday-Thursday (6/14-6/17) 9 a.m. to 3 p.m., Westbound SH 71 left mainlane will be closed from Old Bastrop Hwy to E. Riverside Dr.

Utility Work

6/14/21 to 6/18/21
LANE CLOSURE: US 183 southbound frontage road reduced to one lane Loyola to Techni Center Dr. and by-pass will be closed at MLK Blvd.
Lane Closure | Paving

Lane Closure
Monday-Thursday (6/14-6/17) 8 p.m. to 6 a.m., US 183 southbound frontage road will be reduced to one lane from Loyola to Techni Center Dr. and by-pass will be closed at MLK Blvd. Traffic to travel through signalized intersection at MLK Blvd. to access US 183

Paving

6/14/21 to 6/18/21
RAMP CLOSURE: the southbound US 183 exit ramp to eastbound SH 71 towards Austin Airport will be closed
Ramp Closure | Excavation

Ramp Closure
Monday-Thursday (6/14-6/17) 8 p.m. to 6 a.m., the southbound US 183 exit ramp to eastbound SH 71 towards Austin Airport will be closed. Detour to westbound SH 71 and U-turn at Riverside Drive.

Excavation

6/15/21 to 6/18/21
MOBILE OPERATIONS: Eastbound SH 71 mainlane one lane will be closed from Brandt to E. Riverside Dr.
Lane Closure | Roadway Striping

Lane Closure
Tuesday-Friday (6/15-6/18) 7 a.m. to 5 p.m. Mobile Operation - Eastbound SH 71 mainlane one lane will be closed from Brandt to E. Riverside Dr.

Roadway Striping

6/15/21 to 6/18/21
MOBILE OPERATION: Westbound SH 71 mainlane one lane will be closed Brandt to E. Riverside Dr.
Lane Closure | Roadway Striping

Lane Closure
Tuesday-Friday (6/15-6/18) 9 a.m. to 7 p.m. Mobile Operation - Westbound SH 71 mainlane one lane will be closed from Brandt to E. Riverside Dr.

Roadway Striping

6/15/21 to 6/18/21
LANE CLOSURE: US 183 southbound frontage road closed at Manor Springdale Rd.
Lane Closure | Paving

Lane Closure
Tuesday-Wednesday (6/15-17) 8 p.m. to 6 a.m., US 183 southbound frontage road will be closed at Manor Springdale Rd. Detour eastbound Manor Rd. to Loyola to US 183. North to South U-turn at Manor Springdale Rd. will be closed.

Paving

6/16/21 to 6/18/21
LANE CLOSURE: US 183 northbound right frontage road Eastgate Rd. to Techni Center Dr.
Lane Closure | Guardrail Work

Lane Closure
Monday-Friday (6/14-6/18) 9 a.m. to 3 p.m., US 183 northbound right frontage road will be closed from Eastgate Rd. to Techni Center Dr.

Guardrail Work

6/16/21 to 6/18/21
U-TURN CLOSURE: North to South U-turn at Manor Springdale Rd.
Road Closure | Guardrail Work

Road Closure
Wednesday-Friday (6/16-6/18) 9 a.m. to 3 p.m., North to South U-turn at Manor Springdale Rd. will be closed.

Guardrail Work

6/16/21 to 6/18/21
LANE CLOSURE: US 183 northbound right mainlane Loyola to Manor Springdale Rd.
Lane Closure | Guardrail Work

Lane Closure
Wednesday-Friday (6/16-6/18) 9 a.m. to 3 p.m., US 183 northbound right mainlane will be closed from Loyola to Manor Springdale Rd.

Guardrail Work

6/16/21 to 6/18/21
RAMP CLOSURE: US 183 northbound mainlane at Thompson and the on-ramp at Bolm Rd.
Ramp Closure | Pedestrian Bridge Construction

Ramp Closure
Wednesday-Thursday (6/16-6/17) 8 p.m. to 6 a.m., US 183 northbound mainlane at Thompson and the on-ramp at Bolm Rd. will be closed. Detour via Exit to Montopolis to northbound general-purpose.

Pedestrian Bridge Construction

6/16/21 to 6/20/21
ROAD CLOSURE: US 183 southbound frontage road will be closed at MLK Blvd
Road Closure | Pedestrian Bridge Construction

Road Closure
Wednesday-Thursday (6/16-6/17) 8 p.m. to 6 a.m., Friday (6/18) 8 p.m. to 10 a.m., Saturday (6/19) 6 p.m. to 10 a.m., US 183 southbound frontage road will be closed at MLK Blvd. and the north to south U-turn will be closed at MLK Blvd. Detour via Tannehill Ln. to Techni Center Dr. to US 183

Pedestrian Bridge Construction

6/16/21 to 6/18/21
ROAD CLOSURE: Levander Loop will be closed at Cesar Chavez and at US 183 northbound
Road Closure | Utility Work

Road Closure
Wednesday-Thursday (6/16-6/17) 8 p.m. to 6 a.m., Levander Loop will be closed at Cesar Chavez and at US 183 northbound. Detour via Shady Lane to Cesar Chavez, to southbound US 183 ramp to U-turn at Montopolis Dr.

Utility Work

6/16/21 to 6/18/21
LANE CLOSURE: US 183 northbound left mainlane at Montopolis Dr.
Lane Closure | Drainage Work

Lane Closure
Wednesday-Thursday (6/16-6/17) 8 p.m. to 6 a.m., US 183 northbound left mainlane will be closed at Montopolis Dr.

Drainage Work

6/17/21 to 6/18/21
LANE CLOSURE: Southbound US 183 exit ramp to eastbound SH 71 towards the Austin Airport the left lane will be closed
Lane Closure | Highway Lighting

Lane Closure
Thursday-Friday (6/17-6/18) 9 a.m. to 3 p.m., the southbound US 183 exit ramp to eastbound SH 71 towards Austin Airport the left lane will be closed.

Highway Lighting

6/18/21 to 6/18/21
LANE CLOSURE: US 183 southbound right main lane 51st St. to Techni Center
Lane Closure | Retaining Wall Construction

Lane Closure
Friday (6/18) 9 a.m. to 3 p.m., US 183 southbound right main lane will be closed from 51st St. to Techni Center

Retaining Wall Construction

6/18/21 to 6/20/21
LANE CLOSURE: Westbound Manor Springdale Rd. right lane at US 183
Lane Closure | Paving

Lane Closure
Friday (6/18) 8 p.m. until Sunday (6/20) at 6 p.m., Westbound Manor Springdale Rd. right lane will be closed at US 183.

Paving

6/18/21 to 6/20/21
LANE REDUCTION: US 183 southbound mainlane will be reduced to one lane at US 290
Lane Closure | Paving

Lane Closure
Friday (6/18) 8 p.m. until Sunday (6/20) at 6 p.m., US 183 southbound mainlane will be reduced to one lane at US 290.

Paving

6/20/21 to 6/25/21
LANE REDUCTION: Southbound US 183 exit ramp to eastbound SH 71 towards the Austin Airport will be reduced to one lane
Lane Closure | Excavation

Lane Closure
Sunday (6/20) 6 p.m. to 6 a.m., Monday-Thursday (6/21-6/24) 8 p.m. to 6 a.m., the southbound US 183 exit ramp to eastbound SH 71 towards Austin Airport will be reduced to one lane.

Excavation

Long Term

5/18/21 to 6/21/21
CONTINUOUS ROAD CLOSURE: US 183 northbound frontage road will be reduced to one lane Manor Springdale to US 290.
Lane Closure | Guardrail Work

Lane Closure
Tuesday (5/18) at 9 a.m. until Monday (6/21) at 3 p.m., US 183 northbound frontage road will be reduced to one lane from Manor Springdale to US 290.

Guardrail Work

5/24/21 to 7/31/21
U-TURN CLOSURE: U-turns north of Boggy Creek closed for barrier repairs
Detour | Bridge Construction

Detour
U-turns north of Boggy Creek closed for barrier repairs. Detour to U-turns at MLK and Levander Loop.

Bridge Construction

Sign Up For Our Newsletter

The Mobility Authority sends out E-Newsletters and other announcements to keep neighbors, stakeholders and other interested parties up to date on important activities and events surrounding the construction of this project.