Travel Information

Short Term

8/21/17 to 8/22/17
LANE REDUCTION: US 183 Southbound Towards SH 71
Lane Closure | Guardrail Work

Lane Closure
Monday (8/21) from 8 pm to 6 am, the US 183 southbound mainlanes will be reduced to one lane between Thompson Lane and SH 71, and the ramp to eastbound SH 71 will be reduced to one lane.

Guardrail Work

8/21/17 to 8/26/17
ROAD CLOSURE: Northbound Airport Boulevard at US 183 Northbound
Ramp Closure | Bridge Construction

Ramp Closure
Monday through Friday (8/21-25) from 8 pm to 6 am, the exit to Airport Boulevard, Cesar Chavez, 5th, and 7th Street from northbound US 183 WILL BE CLOSED. Follow signed detour.

Bridge Construction

8/22/17 to 8/26/17
ROAD CLOSURE: Manor/Springdale Road at US 183
Road Closure | Bridge Construction

Road Closure
Tuesday through Thursday (8/22-24) from 8 pm to 6 am, Manor/Springdale Road in both directions will be closed underneath US 183. Follow signed detours.

Bridge Construction

Long Term

4/25/16 to 8/31/17
Bridge Construction at Manor/Springdale Rd Intersection
Road Closure | Bridge Construction

Road Closure
The Texas turnarounds in both directions at Manor/Springdale will be closed for retaining wall and bridge construction. Drivers wishing to complete a turnaround movement will be able to do so at the signalized intersections instead.

Bridge Construction
Workers are rebuilding the US 183 bridge over Manor/Springdale Road.

2/3/17 to 8/31/17
LANE REDUCTION: MLK Blvd
Lane Closure | Bridge Construction

Lane Closure
A major lane reduction will occur along MLK Blvd. between Tannehill Lane & Regency Drive; the roadway will be reduced to 1 lane in each direction. Drivers passing through this interchange may experience increased travel delays.

Bridge Construction
This is to accommodate construction of a new wider bridge at US 183. Once a portion of the new bridge is completed, traffic in both directions will be detoured onto the new bridge so demolition of the old bridge can take place, and the remainder of the new bridge can be constructed.

4/25/17 to 4/30/18
ROAD CLOSURE: Central Avenue & Bluestein Drive
Road Closure | Utility Work

Road Closure
Starting April 25, Central Avenue and Bluestein Drive are temporarily closed at their intersections with northbound US 183 for utility work and will remain closed for approximately 12 months. Traffic is being detoured via Techni Center Drive and Semi-Conductor Drive.

Utility Work

6/5/17 to 9/8/17
ROAD CLOSURE: Levander Loop at the US 183 Northbound Turnaround
Road Closure | Bridge Construction

Road Closure
Continuously between Friday June 5 at 8 pm to Friday September 8 at 6 am, Levander Loop will be closed at the US 183 northbound turnaround. Follow the signed detour.

Bridge Construction

7/17/17 to 8/26/17
CONTINUOUS CLOSURE: North Del Monte Closed at Montopolis
Road Closure | Utility Work

Road Closure
Continuously between Monday July 17 at 7 am and Saturday August 26 at 6 pm, North Del Monte will be closed at Montopolis Drive. Detour via Walker Lane.

Utility Work

8/17/17 to 10/9/17
LANE REDUCTION: 51st Street in Both Directions West of US 183
Lane Closure | Roadway Base Installation

Lane Closure
Continuously from Friday (8/17) at 8 pm to the morning of October 9, 51st Street on the west side of US 183 will be reduced to one lane in both directions between US 183 and Hutchinson Drive.

Roadway Base Installation

Sign Up For Our Newsletter